Project

General

Profile

Actions

QA #2716

closed

QA #1843: [STAG] New Cancellation - QA Test cases

QA #1844: ADMIN

QA #1846: Hotel Plan Master

QA #2240: [Cancellation tab] Hotel, List, Summary, New/Modify/Add/Delete btn, Confirm popup

[Cancellation - New] Incorrectly message is displayed when period options overlap

Added by Holden Dang 3 months ago. Updated about 2 months ago.

Status:
확인(Confirmed)
Priority:
높음(High)
Assignee:
Start date:
01/07/2026
Due date:
01/07/2026
% Done:

100%

Estimated time:
1.00 h
Build env.:
Dev

Description

Pre=condition:
- Admin is logged in
- Hotel and Rate Type data exist in the system
- Navigate to the Cancellation tab

Steps:
1. Search for a hotel
2. Click New button
3. Select Room/Rate type
4. Select Used radio button
5. Enter Default: 25-08-01~25-08-31
6. Enter all required fields
7. Enter Option 1: 25-07-01~25-07-31
8. Enter all required fields
9. Enter Option 1: 25-07-15~25-07-31
10.Enter all required fields
11. Click Save

Actual result: Alert "The option date range is outside the default range. Please check again."
Expected result: Alert 'Duplicate dates exist within option period. Please check again.'


Files

picture676-1.png (134 KB) picture676-1.png Holden Dang, 12/19/2025 07:52 AM
picture676-2.png (132 KB) picture676-2.png Holden Dang, 12/19/2025 07:52 AM
picture690-1.png (120 KB) picture690-1.png Holden Dang, 01/08/2026 04:27 AM
image.png (47.2 KB) image.png Tan Jang, 01/12/2026 07:48 AM
picture574-1.png (121 KB) picture574-1.png Show red border Holden Dang, 01/12/2026 08:10 AM
picture574-2.png (116 KB) picture574-2.png Cannot select past date Holden Dang, 01/12/2026 08:10 AM
Actions #1

Updated by Holden Dang 3 months ago

Expected result: Alert: "Duplicate dates exist within option period. Registration not possible. Please check again."

Actions #2

Updated by Joseph Vo 3 months ago

  • Assignee changed from Joseph Vo to Dan Hoang
Actions #3

Updated by Dan Hoang 2 months ago

  • Assignee changed from Dan Hoang to Tan Jang
Actions #4

Updated by Tan Jang 2 months ago

  • Status changed from 신규(New) to 피드백(Feedback)
  • Assignee changed from Tan Jang to Holden Dang

case này Default: 25-08-01 mà Option 1: 25-07-01 thì báo outside là đúng rồi.

Actions #5

Updated by Holden Dang 2 months ago

  • Assignee changed from Holden Dang to ziniy Kang

Hi Mr. @HYUNAH KANG (ZINIY),
In this case, I created this task based on a previous test case, so there is no alert in the requirement/document. Please review the alert to understand the team’s plan. Thanks.

Actions #6

Updated by ziniy Kang 2 months ago

  • Status changed from 피드백(Feedback) to 진행(Doing)
  • Assignee changed from ziniy Kang to Tan Jang

Pls change text: 'Duplicate dates exist within option period. Please check again.'

Actions #7

Updated by Tan Jang 2 months ago

  • Due date set to 01/07/2026
  • Status changed from 진행(Doing) to 완료(Done)
  • Start date set to 01/07/2026
  • % Done changed from 0 to 100
  • Estimated time set to 1.00 h
Actions #8

Updated by Tan Jang 2 months ago

  • Status changed from 완료(Done) to QA test
  • Assignee changed from Tan Jang to Holden Dang
  • Build env. set to Dev
Actions #9

Updated by Holden Dang 2 months ago

Failed. Please fix it again. Thank you for your help.
Actual result: Show red border in Option 1 and option 2 during the selected period

Actions #10

Updated by Tan Jang 2 months ago

  • Status changed from 완료실패(Failed) to 피드백(Feedback)
  • Assignee changed from Tan Jang to Holden Dang

này validate ở backend nên chỉ có thể trả về message, không tô màu UI được nha Holden.

Actions #11

Updated by Holden Dang about 2 months ago

  • Assignee changed from Holden Dang to Tan Jang

Expected result: Only display the message 'Duplicate dates exist within option period. Please check again.'

Actions #12

Updated by Tan Jang about 2 months ago

  • Status changed from 피드백(Feedback) to QA test
  • Assignee changed from Tan Jang to Holden Dang
Actions #13

Updated by Holden Dang about 2 months ago

  • Status changed from QA test to 피드백(Feedback)
  • Assignee changed from Holden Dang to ziniy Kang

Hi Mr. @HYUNAH KANG (ZINIY),
Please review and confirm whether the actual result or the expected result. Thank you!

Actual result: Show red border in Option 1 and Option 2 during the selected period
Expected result: Alert 'Duplicate dates exist within option period. Please check again.'

Actions #14

Updated by ziniy Kang about 2 months ago

Pls change text: 'Duplicate dates exist within option period. Please check again.'

Actions #15

Updated by Holden Dang about 2 months ago

  • Assignee changed from ziniy Kang to Tan Jang
Actions #16

Updated by Tan Jang about 2 months ago

  • File image.png image.png added
  • Status changed from 피드백(Feedback) to QA test
  • Assignee changed from Tan Jang to Holden Dang


Chốt lại không cho chọn option ngoài default trên UI.

Actions #17

Updated by Holden Dang about 2 months ago

Expected result:
- Show red border in Option 1 and Option 2 during the selected period
- Cannot select past date

Tested Dev env => Passed

Actions #18

Updated by ziniy Kang about 2 months ago

  • Status changed from 완료(Done) to 확인(Confirmed)
Actions