결함(Bug) #1352

closed

결함(Bug) #1329: Login issue

[PC] Fix Booking Code Display & Update Resend Button Color

Added by ziniy Kang 6 months ago. Updated 4 months ago.

Status:
완료성공(Resolve)
Priority:
보통(Normal)
Assignee:
Start date:
09/08/2025
Due date:
09/16/2025
% Done:

100%

Estimated time:
2.00 h
Part:
Build env.:
Prod

Description

1. Khi nhập mã code để search booking, mã số ko hiển thị đầy đủ mà bị mất nửa bên phải
→ Cần fix lại cho mã code hiển thị đầy đủ.
2. Btn ‘Resend verification code’ khi ở trạng thái enable thì sẽ có màu cam


Files

picture432-1.png (117 KB) picture432-1.png ziniy Kang, 09/01/2025 06:23 AM
picture915-1.png (139 KB) picture915-1.png verify code Tracy Truong, 09/11/2025 07:27 AM
picture915-2.png (111 KB) picture915-2.png Resend verification code Tracy Truong, 09/11/2025 07:27 AM
picture197-1.png (81.5 KB) picture197-1.png Tracy Truong, 09/15/2025 02:27 AM
picture197-2.png (165 KB) picture197-2.png Tracy Truong, 09/15/2025 02:27 AM
picture468-1.png (531 KB) picture468-1.png Tracy Truong, 09/22/2025 08:29 AM
picture328-1.png (837 KB) picture328-1.png Tracy Truong, 10/31/2025 02:59 AM
picture328-2.png (846 KB) picture328-2.png Tracy Truong, 10/31/2025 02:59 AM
picture328-3.png (754 KB) picture328-3.png Tracy Truong, 10/31/2025 02:59 AM
picture328-4.png (537 KB) picture328-4.png Tracy Truong, 10/31/2025 02:59 AM
Actions #2

Updated by Joseph Vo 6 months ago

  • Assignee changed from Joseph Vo to Tri Thien (Edward) Mai
Actions #3

Updated by Tri Thien (Edward) Mai 6 months ago

  • Due date set to 09/10/2025
  • Status changed from 신규(New) to 진행(Doing)
  • Start date set to 09/08/2025
  • Estimated time set to 2.00 h
Actions #4

Updated by Tri Thien (Edward) Mai 6 months ago

  • % Done changed from 0 to 100
Actions #5

Updated by Tri Thien (Edward) Mai 6 months ago

  • Status changed from 진행(Doing) to 완료(Done)
Actions #6

Updated by Tri Thien (Edward) Mai 6 months ago

  • Build env. set to Dev
Actions #7

Updated by Tri Thien (Edward) Mai 6 months ago

  • Status changed from 완료(Done) to QA test
  • Assignee changed from Tri Thien (Edward) Mai to Tracy Truong

Hi Tracy Truong, please help me test on dev environment. Thanks!

Actions #8

Updated by Tracy Truong 6 months ago

Checked on Dev
1. Display full number of verification code => ok
2. Btn ‘Resend verification code’ will be changed to orange color when enable => ok
But in Vi, EN : lack of space in text (as red bolder in capture)
As -is: 30giây/ 30seconds
To-be: 30 giây/ 30 seconds
Please fix it, thank you

Actions #9

Updated by Tri Thien (Edward) Mai 6 months ago

  • Status changed from 완료실패(Failed) to 진행(Doing)
Actions #10

Updated by Tri Thien (Edward) Mai 6 months ago

  • Due date changed from 09/10/2025 to 09/16/2025

Fixed issue failed as the note above.

Actions #11

Updated by Tri Thien (Edward) Mai 6 months ago

  • Status changed from 진행(Doing) to QA test
  • Assignee changed from Tri Thien (Edward) Mai to Tracy Truong

Hi Tracy Truong, please help me retest this issue on dev environment. Thanks!

Actions #12

Updated by Tracy Truong 6 months ago

Rechecked on Dev, ok

Actions #13

Updated by ziniy Kang 6 months ago

  • Status changed from 완료(Done) to 확인(Confirmed)
Actions #14

Updated by Tri Thien (Edward) Mai 6 months ago

  • Status changed from 확인(Confirmed) to 완료(Done)
  • Build env. changed from Dev to Staging
Actions #15

Updated by Tri Thien (Edward) Mai 6 months ago

  • Status changed from 완료(Done) to QA test
  • Assignee changed from Tri Thien (Edward) Mai to Tracy Truong

Hi Tracy Truong please help me test this issue on Staging env. Thank you!

Actions #16

Updated by Tracy Truong 6 months ago

Checked on STAG, ok

Actions #17

Updated by ziniy Kang 6 months ago

  • Status changed from 완료(Done) to 확인(Confirmed)
  • Assignee changed from Tri Thien (Edward) Mai to Mon Nguyen
Actions #18

Updated by Mon Nguyen 5 months ago

  • Assignee changed from Mon Nguyen to harry harry

Dear harry harry
Please help me follow up this task on the next step
Thank you

Actions #19

Updated by harry harry 4 months ago

  • Build env. changed from Staging to Prod
Actions #20

Updated by ziniy Kang 4 months ago

  • Status changed from 확인(Confirmed) to 중단 (Stop)
Actions #21

Updated by ziniy Kang 4 months ago

  • Status changed from 중단 (Stop) to QA test
  • Assignee changed from harry harry to Tracy Tran
Actions #22

Updated by Tracy Truong 4 months ago

Checked on Prod, ok

Actions